Chinyere agreed to make a dress for Halima with... - JAMB Commerce 2018 Question
Chinyere agreed to make a dress for Halima with September 20, 1995 as the delivery date. If the dress was not ready at that date, Halima could
A
Seize another gown from Chinyere’s shop
B
Regard the contract between them as terminated
C
Sue Chinyere for specific performance
D
Sue Chinyere for damages
correct option: b
Halimah can regard the contract as being terminated because this is a case of breach of contract.
Breach of contract is a legal cause of action and a type of civil wrong, in which a binding agreement or bargained-for exchange is not honored by one or more of the parties to the contract by non-performance or interference with the other party's performance.Please share this, thanks:
Add your answer
No responses