If 4 workers can finish a job in 8 days, how many days will it take for 8 workers to finish the same job?
View related lesson
Ask EduPadi AI for a detailed answer
Using inverse proportion:
4×8=8×𝑑,
so 𝑑=32/8= 4 days.